PIER B RESORT & HOTEL

Duluth, Minnesota

FEATURES

  • 4-story resort

  • 140 guest rooms

  • Indoor pool and spa

  • Environmental compliance

NORDIC Group, Inc. provided underwater inspections, demolition, earthwork, construction oversight/inspection, and capping of contaminated soil. Capping of legacy contaminants in Slip 2 involved the development of a public and private partnership that included the developer, the MPCA, Army Corps of Engineers and the Minnesota MDNR. The capping project placed a minimum of 2.8 feet of clean dredge sediments across the 2+ acre slip. The dredge material used was pre-screened for structural and chemical characteristics and obtained from the Army Corps of Engineers dredging operations. An additional 7 feet of dredge material was placed above the cap to provide structural support to the aging pier walls and to provide protected shallow water habitat.

Previous
Previous

Park Creek Pond

Next
Next

Pier B Retractable Bridge